Week three.

Work progresses on the bedroom walls.

Each hollow block wall is reinforced with 10 millimeter rebar, spaced vertically every one meter and horizontally every other course of blocks.

And at the end of week three, all bedroom walls are up and the shuttering is removed from the last post.

The two remaining beams to be made are across the top of the firewall at the back of the house and the other at the side, extending from the back to the currently solitary post.

Here you can see the shuttering on half of the last beam and the rebar cage at the front half, which will support the roofing above the patio.

End of week four!

 

continue to week five